| Item Number | WTF15F04246109 |
| Structural inspection completion | 2015-04-08 18:00 |
| Check the data completion | 2015-04-10 18:00 |
| Test completion | 2015-04-14 18:00 |
| Draft Report | 2015-04-16 18:00 |
| Requirements closing | 2015-04-17 18:00 |
| Structural Inspection Engineer | Ali Lu |
| Data processing engineer | Nicol He |
| Report Engineer | Chat Yu |
| Report of auditor | Jack Li |
| Test Technician | |
| Test schedule | |
| Test completion | |
| Heavy test schedule | No |
| Test the actual completion | |
| Letter project |
Detailed log
| Item Number | Operation Content | Date | Remark | Operator |
| WTF15F04246109 | Add Case | 2015-04-03 9:32:37 | Beck feng | Eren Chen |
| WTF15F04246109 | Submit financial approval | 2015-04-03 9:52:33 | Beck feng | Eren Chen |
| WTF15F04246109 | Financial through the approval | 2015-04-03 10:23:27 | Beck feng | Eren Chen |
| WTF15F04246109 | The auditor through the approval | 2015-04-03 15:18:06 | Beck feng | Eren Chen |
| WTF15F04246109 | Project Manager through the approval | 2015-04-03 16:25:12 | Beck feng | Eren Chen |